MoDOT planned road work in north Missouri for the week of April 18, 2024

Road Maintenance News Graphic
Share To Your Social Network

The following is a list of general highway maintenance and construction work the Missouri Department of Transportation has planned in North Missouri for the week of April 8-14.

Inclement weather may cause schedule changes in some of the planned work. There also may be moving operations throughout the region, in addition to the work mentioned below.

Andrew County

  • U.S. Route 59 – Resurfacing project from Business U.S. 71 to Country Club Road through mid-April (Contractor: Herzog Contracting Corp.).
  • U.S. Route 71 – Resurfacing project from the intersection of Route T near Savannah to the intersection of Business Route 71 near Maryville through mid-October (Contractor: Herzog Contracting Corp.).

Atchison County

  • Route 46 – CLOSED for a bridge replacement project at the Little Tarkio Creek east of Fairfax, through May 2024. (Contractor: North Central Bridge, LLC) 
  • Interstate 29 – Pothole patching from the Iowa state line to the Holt County line, April 15-19.
  • U.S. Route 136 – Pothole patching from the Nodaway County line to the Nebraska state line, April 16-18.

Buchanan County

  • U.S. Route 169 – Resurfacing project from Route FF in Buchanan County to the Clinton/Clay County line through August 2024 (Contractor: Emery Sapp & Sons).
  • Route 752  – Resurfacing project from 22nd Street to U.S. Route 59 through mid-April (Contractor: Herzog Contracting Corp.).
  • Route AC – Intersection and ADA improvements at Messanie Street through mid-May (Contractor: Herzog Contracting Corp.).

Caldwell County

  • Route 13 – CLOSED from Far West Drive to Kingston for a resurfacing project from the south city limits of Hamilton to just north of Route HH in Kingston through mid-June. (Contractor: Phillips Hardy, Inc.)

Chariton County

  • Route 11 – Pothole patching from Route E to U.S. Route 24, April 15-19.
  • Route C – CLOSED for a culvert replacement project from 8 a.m. to 3 p.m. daily at the following locations and dates:

               April 15 – Hurricane Branch Avenue to St. Joseph Avenue.
               April 16-17 – St. Joseph Avenue to Siloam Avenue.
              April 18 – Siloam Avenue to Route F.

  • Route KK – CLOSED for surveying at the bridge over the Little Chariton River, April 15, 9 a.m. to 4 p.m. daily.
  • Route HH – CLOSED at the Bee Creek Bridge for a bridge rehabilitation project through mid-July. (Contractor: Capital Paving and Construction, LLC). 
  • Route 5 – Resurfacing project from U.S. Route 24 to Route KK through May.

Clinton County

  • Route H – CLOSED for a bridge replacement project from NE Estep Road to U.S. Route 69 through November 2024. (Contractor: Phillips Hardy, Inc.) 
  • U.S. Route 169 – Resurfacing project from the Clinton/Clay County line to Route FF in Buchanan County through August 2024 (Contractor: Emery Sapp & Sons).
  • I-35 – Concrete replacement southbound from mile marker 45 to mile marker 42, April 8-12. The road will be narrowed to one lane around the clock with a 12-foot width restriction.

DeKalb County

  • Route E – CLOSED daily in 2-mile sections for a resurfacing project from Route A to U.S. Route 69, April 8-14 (Herzog Contracting Corp.).
  • Route D – CLOSED daily in 2-mile sections for a resurfacing project from Route 6 to Pleasant Road, April 8-14 (Herzog Contracting Corp.).
  • U.S. Route 36 – Concrete replacement eastbound at the Osborn junction, April 15-16. The road will be narrowed to one lane around the clock.
  • U.S. Route 36 – Concrete replacement eastbound at the Reservoir Road, April 16-18. The road will be narrowed to one lane around the clock.

Gentry County

  • Route YY – CLOSED for a bridge replacement project at the Bear Creek Bridge through April 2024. (Contractor: Gene Haile Excavating, Inc.) 
  • Route DD – CLOSED for a culvert replacement from Route C to County Road 600, April 16, 8 a.m. to 3 p.m.
  • U.S. Route 169 – Drainage work southbound at 280th Street, April 15.

Harrison County

  • I-35 – pavement repair north and southbound from Eagleville to Bethany, April 15-19.

Linn County

  • U.S. Route 36 – Bridge maintenance at the Muddy Creek Bridge, April 15-18, 8:30 a.m. to 2:30 p.m. daily. The bridge will be down to one lane with a 12-foot width restriction during working hours.

Livingston County

  • Route D – CLOSED until further notice at the Rattlesnake Creek Bridge due to deterioration. This bridge is included for replacement in the Northwest Bridge Bundle. Construction is tentatively scheduled to begin on April 22.
  • Route D – Sidewalk improvements in Ludlow through April. (Contractor: BRS Construction, LLC). 
  • U.S. Route 36 – Resurfacing and pavement improvement project from the Coon Creek bridge in Chillicothe to the Caldwell County line through June. One lane may be closed in either direction around the clock. A 15-foot width restriction will be in place with a 10-foot width restriction under the U.S.Route 65 bridge and the Kansas City Sub railroad bridge in Chillicothe (Contractor: Magruder Paving, LLC).

Mercer County

  • Route W – CLOSED for a culvert replacement from Bison Place to Arizona Street, April 16, 7 a.m. to 3 p.m.
  • Route E – CLOSED for a culvert replacement from U.S. Route 65 to Route Y, April 17, 7 a.m. to 3 p.m.

Nodaway County

  • Route NN – CLOSED around the clock for bridge maintenance from Panther Road to Orion Road, April 15-19.

Worth County

  • U.S. Route 169 – Resurfacing and slide repair project from the Iowa State line to just north of Route 46 through July 2024 (Contractor: Herzog Contracting Corp.).

Share To Your Social Network